§ 62-614. Determination of proportionate fair-share obligation.
(a)
Proportionate fair-share mitigation for concurrency impacts may include, without limitation, separately or collectively, private funds, contributions of land, and construction and contribution of facilities.
(b)
A development shall not be required to pay more than its proportionate fair-share. The fair market value of the proportionate fair-share mitigation for the impacted facilities shall not differ regardless of the method of mitigation.
(c)
The methodology used to calculate an applicant's proportionate fair-share obligation shall be as provided for in F.S. § 163.3180(12), as follows:
"The cumulative number of trips from the proposed development expected to reach roadways during peak hours from the complete build out of a stage or phase being approved, divided by the change in the peak hour maximum service volume (MSV) of roadways resulting from construction of an improvement necessary to maintain the adopted LOS, multiplied by the construction cost, at the time of developer payment, of the improvement necessary to maintain the adopted LOS."
OR
Proportionate Fair-Share = σ [[(Development Trips;sub \sub;)/(SV Increase;sub \sub;)] × Cost;sub \sub;]
Where: Development Trips;sub \sub; = Those trips from the stage or phase of development under review that are assigned to roadway segment "i" and have triggered a deficiency per the CMS; SV Increase;sub \sub; = Service volume increase provided by the eligible improvement to roadway segment "i" per section E; Cost;sub \sub; = Adjusted cost of the improvement to segment "i". Cost shall include all improvements and associated costs, such as design, right-of-way acquisition, planning, engineering, inspection, and physical development costs directly associated with construction at the anticipated cost in the year it will be incurred. (d)
For the purposes of determining proportionate fair-share obligations, the county shall determine improvement costs based upon the actual cost of the improvement as obtained from the CIE, the MPO/TIP or the FDOT Work Program. Where such information is not available, improvement cost shall be determined using one of the following methods:
(1)
An analysis by the county of costs by cross section type that incorporates data from recent projects and is updated annually and approved by the board of county commissioners. In order to accommodate increases in construction material costs, project costs shall be adjusted by an inflation factor established by or acceptable to the county; or
(2)
The most recent issue of FDOT Transportation Costs, as adjusted based upon the type of cross-section (urban or rural); locally available data from recent projects on acquisition, drainage and utility costs; and significant changes in the cost of materials due to unforeseeable events. Cost estimates for state road improvements not included in the adopted FDOT work program shall be determined using this method in coordination with the FDOT district.
(e)
If the county has accepted an improvement project proposed by the applicant, then the value of the improvement shall be determined using one of the methods provided in this section.
(f)
If the county has accepted right-of-way dedication for the proportionate fair-share payment, credit for the dedication of the non-site related right-of-way shall be valued on the date of the dedication at 125 percent of the most recent assessed value by the county property appraiser or, at the option of the applicant, by fair market value established by an independent appraisal approved by the county and at no expense to the county. The applicant shall supply a drawing and legal description of the land and a certificate of title or title policy insuring title of the land to the county at no expense to the county. If the estimated value of the right-of-way dedication proposed by the applicant is less than the county estimated total proportionate fair-share obligation for that development, then the applicant must also pay the difference. Prior to purchase or acquisition of any real estate or acceptance of donations of real estate intended to be used for the proportionate fair-share, public or private partners should contact the FDOT for essential information about compliance with federal law and regulations.
(Ord. No. 06-60, § 1, 11-14-06)