§ 62-1156. Issuance of building permit for property abutting end of road right-of-way.  


Latest version.
  • A building permit may be issued to property abutting the termination of a dedicated and accepted road right-of-way, regardless of whether the frontage is less than the required minimum frontage on a dedicated and accepted road right-of-way, under the following conditions:

    (1)

    There must be compliance with all other provisions of this article or related sections of this Code;

    (2)

    The frontage on the road right-of-way must be at least 50 percent of the width of the road right-of-way; and

    (3)

    A turnaround must be constructed at the end of the road right-of-way by the property owner.